Singapore Government
Link to AGC Website
Home | Search | Browse | Results | My Preferences
 
Contents

Long Title

Part I PRELIMINARY

Part II MASTER PLAN AND CONSERVATION AREAS AND GUIDELINES

Part III DEVELOPMENT AND SUBDIVISION OF LAND

Part IV ENFORCEMENT

Part V DEVELOPMENT CHARGES

Part VA TEMPORARY DEVELOPMENT LEVY

Part VI RECOVERY OF MONEYS

Part VII MISCELLANEOUS

Part VIII TRANSITIONAL AND SAVING PROVISIONS

FIRST SCHEDULE Qualified Persons

SECOND SCHEDULE Uses

THIRD SCHEDULE

Legislative History

 
Slider
Left Corner
Print   Permalink
On 24/05/2013, you requested for the version in force on 24/05/2013 incorporating all amendments published on or before 24/05/2013. The closest version currently available is that of 01/07/2009.
Slider
Expiry of permissions
20.
—(1)  Except where the competent authority imposes a condition to the contrary, every planning permission and every conservation permission shall lapse if the development or works authorised by it are not completed or effected within 2 years of —
(a)
the date of the grant of the planning permission or conservation permission, as the case may be;
(b)
the date of the final permission granted under section 17(4); or
(c)
if an appeal is made under section 22, the date the appeal is determined or withdrawn.
(2)  The competent authority may, in his discretion, extend any planning permission or conservation permission on such terms and for such further period as he thinks fit.